Oct. 6, 2017: Fall has arrived, and that means some of the final touches are being done on a couple of Lakewood’s building and expansion projects.
Staples Clinic
- The first-floor drywall hanging and taping is completed, and 60% of that floor is painted.
- Drywall on the lower level is 50% complete, and painting will begin next week.
- The ceiling grid is done on both levels, ceramic tile is done on all but two restrooms, and doors and hardware are on-site.
- All but a few windows are in, and casework for the remaining ones will begin next week.
- All curb and guttering is completed, and light fixtures will start being installed next week.
- Turnover for the clinic addition is on schedule for November 27th, which means equipment installs and final cleaning will take place that week, and furniture move-in will be the next week.
- The hope is to start seeing patients in the new addition starting December 11th.
MRI/ED
- The MRI is placed in the MRI suite and the magnet will be started up on Monday. Calibration will take 2-3 weeks.
- Painting is occurring in the remodeled ED area as well as the MRI prep room and dressing room.
- Ceiling grid, doors and hardware will be placed next week.
- Flooring will be installed the week of the 16th.
- Turnover will occur on the 23rd, and should be completed by the 27th.
Pillager Clinic
- Drywall hanging and taping will be completed by the 11th, and painting and tiling will occur the week after.
- Turnover will be November 20th, which is Thanksgiving week. The hope is to start seeing patients in the remodeled area on November 27th.